Technical
-> Transformer Power Ratings
 |
 |
 |
 |
Transformer Power Ratings |
|
 |
 |
 |
 |
In many circumstances the power required by the load is equivalent
to the rating of the transformer expressed in either VA or
KVA e.g. 1KW (1000 Watts) load requires a 1KVA transformer.
However this is not always the case as per the following examples
Load Efficiency
In this case the load is specified for the work it can perform.
I.e. A 10KW motor can do 10KW of work however the motor will
have an efficiency η that will define the power the motor
itself dissipates while performing its work. The transformer
will have to deliver the power for the work the motor performs
and the power it dissipates
The transformer rating will be given by 
Power Factor
When supplying a resistive load the current flowing
is directly proportional to the applied voltage instantaneous
voltage. The current and voltage waveforms for an AC voltage
input appear as in the figure. |
 |
| If we consider either a purely inductive or capacitor
load the peak of the current will be shifted in relation
to the voltage peak by an angle of +90° or -90° |
 |
In reality a load will be predominantly resistive with
inductive and or capacitive components, in such cases
we find that the amplitude of the current bears a direct
relationship to the applied voltage however the peak of
the wave occurs at an arbitrarily shifted position as
demonstrated by φ |
 |
The current is said to have a phase angle ‘φ’
in relation to the voltage and the power is given by the equation

cos φ is known as the Power Factor it is defined as
the difference between the real power and the apparent power
The effects of power factor also compound with those of load
efficiency. Thus for a transformer to deliver power to a motor
of efficiency η and with a power factor cos φ the
rating is given by

Typically this results in required 
Duty Cycle
If we consider a situation whereby a transformer is powering
a piece of equipment that is operating continuously on load
e.g. a water pump draining an area where water is flooding
in, the transformer would have to be fully rated for the power
consumption of the pump. If the flooding were less severe
the pump may only be turned on for a specific time period
each hour just to reduce the water depth to an acceptable
level, the time the pump is operational divided by the total
time available expressed as a percentage is known as the Duty
Cycle

When a transformer operates with a duty cycle, ON for a time
at maximum load, KVAMax then OFF for the remaining time during
a cyclic period the required size of the unit can be reduced
according to the formulae

For complex duty cycles with different loading levels for
different parts of the cycle
E.g. A large machine with a cooling pump. The machine operates
at full power “L” for 30% of the time and just
the cooling pumps at a power level “l” for the
remaining 70% of the cycle

Generally this equation can be written
Where T is the period of the cycle
Portable Tools Transformers
Intermittent rated portable tool transformers are a specific
example of transformers designed for operation with a defined
duty cycle.
The standard BSEN 61558 specifies a repetitive intermittent
duty cycle of 25% i.e. 5 minutes on at maximum rated load
then 15 minutes off. This results in a heating and cooling
cycle on the units that will ultimately stabilize at the maximum
permitted temperature of operation.
A 25% duty cycle equates to a maximum continuous loading
equivalent to half of the intermittent rate loading. E.g.
a 3.3kVA intermittent rated transformer can deliver 1.65kVA
continuously
Non-linear Loads
Transformers that are subject to loads with large harmonic
content e.g. those delivering power to a large number of DC
power supplies also have to have their ratings adjusted for
the self heating effects of the harmonics. The harmonic spectrum
of the load can be defined by its K-Factor and transformers
designed for these applications are referred to as K-Factor
transformers
|