Technical
-> Cast Resin Transformer Testing
 |
 |
 |
 |
Cast
Resin Transformer Testing
|
|
 |
 |
 |
 |
As routine Cast Resin Transformers are subject to the following
factory testing prior to approval for dispatch
Routine testing
- Dielectric Withstand Test
- Induced Voltage Test
- Voltage Ratio Test
- No-load Current Measurement
- No-load Power Loss Measurement
- Winding Resistance Measurement
- Short Circuit Impedance Test
- Partial Discharge Test
To obtain the approval of these types of transformer units
have been submitted to independent test houses for formal
Type Testing. The following have been conducted
- Lightning Impulse Test *
- Temperature Rise Test *
- Acoustic Noise Level Test *
- Short Circuit Withstand Test
- Zero Sequence Impedance Test
- Condensation
- Condensation and Humidity Penetration
- Fire Behaviour
Facility is offered to customers to witness the routine tests
and if required the three type tests marked with an asterisk.
|